Our scope
Reinforcement, formwork, concreting, precast installation and masonry within the package assigned to Nide Works. Work follows the construction drawings and sequence agreed with site management.
Auderghem · Brussels · Client : VDS / Peremans · Assignment confirmed · planned start 29 October 2026
Nide Works is preparing the structural works for Côté Colline in Auderghem, in coordination with VDS / Peremans. The first package covers the foundations and the two lift areas.
Reinforcement, formwork, concreting, precast installation and masonry within the package assigned to Nide Works. Work follows the construction drawings and sequence agreed with site management.
The planned start is 29 October 2026, with the first foundation and lift-area package due by 6 November. A broader restart is planned for December, subject to the detailed programme.
The programme describes agreed or provisional stages. It is not a record of completed progress.
Send your drawings, bill of quantities and constraints. We review your work package and confirm the next steps.