Our scope
16 foundation footings: formwork, reinforcement and concrete. Phase 1: install and adjust shoring to the approved plan, install 146.40 m² of slabs, additional reinforcement and concrete topping.
Hasselt · Client : Houben & Vanderstraeten · In progress · 2026
At Hasselt, Nide Works is working on the external stair and balcony foundations, followed by a lattice slab floor approximately 8.5 metres above ground.
16 foundation footings: formwork, reinforcement and concrete. Phase 1: install and adjust shoring to the approved plan, install 146.40 m² of slabs, additional reinforcement and concrete topping.
Coordinate lifting and check bearings, levels and reinforcement before pouring. Shoring remains until the engineer releases it. The 5.20 t of additional reinforcement is provisional, subject to the final bar schedule. Phase 2 of 8.67 m² is excluded.
Planned quantities within the assigned scope. Actual progress is recorded separately on site.
| Work item | Reference quantity |
|---|---|
| Foundation footings | 16 pcs |
| Foundation concrete | 28.653 m³ |
| Foundation reinforcement | 4.55567 t4,555.67 kg |
| Foundation side formwork | 50.58 m² |
| Slab installation · phase 1 | 146.4 m² |
| Concrete topping · phase 1 | 25.42 m³ |
| Additional reinforcement · phase 1Provisional | 5.2 t5,200 kg |
Structural work, new construction or tender: send the scope, bill of quantities and constraints. We qualify the file after reviewing the dossier before confirming the next step.