Our scope
Structural works and façade masonry within the contractual scope agreed with D’Hulst. Work organisation follows the construction drawings, access requirements and site sequencing.
Verbrande-Entrepotstraat 7 · Antwerp · Client : D’Hulst · Order confirmed · preparation for 2027
The project on Verbrande-Entrepotstraat combines offices, storage areas, housing and a basement. Nide Works is responsible for the structural works and façade masonry package assigned by D’Hulst.
Nide Works is preparing the structural works and façade masonry package for D’Hulst at THEO Glasfabriek in Antwerp. The order is confirmed, with work planned for 2027.
Structural works and façade masonry within the contractual scope agreed with D’Hulst. Work organisation follows the construction drawings, access requirements and site sequencing.
The provisional start is in weeks 7–8 of 2027, with work planned through weeks 37–38. The exact start date will be communicated two weeks in advance.
The programme describes agreed or provisional stages. It is not a record of completed progress.