PROJECT BRIEF / STRUCTURAL WORKS

UBICENTER II — Leuven

In Leuven, Nide Works is carrying out structural works for UBICENTER II with the Cordeel–Democo joint venture at Philipssite 7. Work has been in progress since October 2026.

Architectural rendering of the UBICENTER II office complex in Leuven (credit: ViRiX / De Gregorio & Partners).
ARCHITECTURAL RENDERING · CREDIT: VIRIX / DE GREGORIO & PARTNERS

Architectural rendering of the overall project. Nide Works scope: structural works (columns, slabs, supplementary concrete, walls and infill of twin-wall precast panels), for Cordeel–Democo.

Client / location
Cordeel–Democo · Philipssite 7, 3000 Leuven
Nide Works package
Structural works
Status / period
In progress · 2026
UBICENTER II — architectural rendering of the future project. Source: ViRiX / De Gregorio & Partners.
Architectural renderingUBICENTER II — architectural rendering of the future project. Source: ViRiX / De Gregorio & Partners.
Planned reinforcement
61,093 t
Planned concrete
1 296,51 m³
Schedule items
25

Nide Works scope

Our scope.

In Leuven, Nide Works is carrying out structural works for UBICENTER II with the Cordeel–Democo joint venture at Philipssite 7. Work has been in progress since October 2026.

Columns, cast-in-place slabs, additional concrete on lattice and hollow-core slabs, cast-in-place walls and twin-wall infill. The schedule covers 61.093 t of reinforcement and 1,296.51 m³ of concrete, detailed below. Seven additional items distinguish plywood, exposed concrete, soffits, horizontal joint, high-level work and the sample panel.

Interfaces and organisation

Formwork, cleaning, oiling, openings, shoring and stripping follow approved construction drawings; check bearings, reinforcement and levels before pouring. Finishes and high-level work partly cover the same areas and must not be added into a total surface. The horizontal joint retains the contract’s 70.34 m², with its unit to be confirmed at measurement. Quantities from contract, table B.1 dated 25/09/2026; no independent geometric remeasurement. Photographs dated 20 October 2026 show progress and the surrounding site; they do not attribute the entire project to Nide Works. The separate future-project visualization is sourced from ViRiX / De Gregorio & Partners.

Planned reference quantities

ItemQuantityUnit
Columns · formwork477m2 · Provisional
Columns · reinforcement10,440kg · Provisional
Columns · concrete58.99m3 · Provisional
Cast-in-place slabs · formwork364.75m2 · Provisional
Slabs · 20 cm edge formwork28m · Provisional
Cast-in-place slabs · reinforcement12,007kg · Provisional
Cast-in-place slabs · concrete120.07m3 · Provisional
On lattice slabs · reinforcement2,660kg · Provisional
On lattice slabs · 20 cm edge formwork26m · Provisional
On lattice slabs · concrete26.6m3 · Provisional
On hollow-core slabs · reinforcement27,546kg · Provisional
On hollow-core slabs · 40 cm edges96m · Provisional
On hollow-core slabs · concrete topping742.29m3 · Provisional
Walls · double-sided formwork, contract measurement422m2 · Provisional
Cast-in-place walls · reinforcement8,440kg · Provisional
Cast-in-place walls · concrete84.44m3 · Provisional
Twin walls · opening formwork100m · Provisional
Twin walls · concrete infill by bucket264.12m3 · Provisional
Additional work · plywood formwork face277.5m2 · Provisional
Additional finish · exposed concrete, one face422m2 · Provisional
Additional finish · exposed landing soffits133m2 · Provisional
Additional finish · horizontal joint, contract unit70.34m2 · Provisional
Additional work · columns > 4 m, up to 5.66 m25m2 · Provisional
Additional work · floor formwork > 2.50 m, up to 6.52 m364.75m2 · Provisional
Exposed concrete sample panel · minimum1m2