PROJECT BRIEF / STRUCTURAL WORKS
UBICENTER II — Leuven
In Leuven, Nide Works is carrying out structural works for UBICENTER II with the Cordeel–Democo joint venture at Philipssite 7. Work has been in progress since October 2026.

Architectural rendering of the overall project. Nide Works scope: structural works (columns, slabs, supplementary concrete, walls and infill of twin-wall precast panels), for Cordeel–Democo.
- Client / location
- Cordeel–Democo · Philipssite 7, 3000 Leuven
- Nide Works package
- Structural works
- Status / period
- In progress · 2026

- Planned reinforcement
- 61,093 t
- Planned concrete
- 1 296,51 m³
- Schedule items
- 25
Nide Works scope
Our scope.
In Leuven, Nide Works is carrying out structural works for UBICENTER II with the Cordeel–Democo joint venture at Philipssite 7. Work has been in progress since October 2026.
Columns, cast-in-place slabs, additional concrete on lattice and hollow-core slabs, cast-in-place walls and twin-wall infill. The schedule covers 61.093 t of reinforcement and 1,296.51 m³ of concrete, detailed below. Seven additional items distinguish plywood, exposed concrete, soffits, horizontal joint, high-level work and the sample panel.
Interfaces and organisation
Formwork, cleaning, oiling, openings, shoring and stripping follow approved construction drawings; check bearings, reinforcement and levels before pouring. Finishes and high-level work partly cover the same areas and must not be added into a total surface. The horizontal joint retains the contract’s 70.34 m², with its unit to be confirmed at measurement. Quantities from contract, table B.1 dated 25/09/2026; no independent geometric remeasurement. Photographs dated 20 October 2026 show progress and the surrounding site; they do not attribute the entire project to Nide Works. The separate future-project visualization is sourced from ViRiX / De Gregorio & Partners.
Planned reference quantities
| Item | Quantity | Unit |
|---|---|---|
| Columns · formwork | 477 | m2 · Provisional |
| Columns · reinforcement | 10,440 | kg · Provisional |
| Columns · concrete | 58.99 | m3 · Provisional |
| Cast-in-place slabs · formwork | 364.75 | m2 · Provisional |
| Slabs · 20 cm edge formwork | 28 | m · Provisional |
| Cast-in-place slabs · reinforcement | 12,007 | kg · Provisional |
| Cast-in-place slabs · concrete | 120.07 | m3 · Provisional |
| On lattice slabs · reinforcement | 2,660 | kg · Provisional |
| On lattice slabs · 20 cm edge formwork | 26 | m · Provisional |
| On lattice slabs · concrete | 26.6 | m3 · Provisional |
| On hollow-core slabs · reinforcement | 27,546 | kg · Provisional |
| On hollow-core slabs · 40 cm edges | 96 | m · Provisional |
| On hollow-core slabs · concrete topping | 742.29 | m3 · Provisional |
| Walls · double-sided formwork, contract measurement | 422 | m2 · Provisional |
| Cast-in-place walls · reinforcement | 8,440 | kg · Provisional |
| Cast-in-place walls · concrete | 84.44 | m3 · Provisional |
| Twin walls · opening formwork | 100 | m · Provisional |
| Twin walls · concrete infill by bucket | 264.12 | m3 · Provisional |
| Additional work · plywood formwork face | 277.5 | m2 · Provisional |
| Additional finish · exposed concrete, one face | 422 | m2 · Provisional |
| Additional finish · exposed landing soffits | 133 | m2 · Provisional |
| Additional finish · horizontal joint, contract unit | 70.34 | m2 · Provisional |
| Additional work · columns > 4 m, up to 5.66 m | 25 | m2 · Provisional |
| Additional work · floor formwork > 2.50 m, up to 6.52 m | 364.75 | m2 · Provisional |
| Exposed concrete sample panel · minimum | 1 | m2 |
Project visuals
Each caption identifies the type of visual and its context.